gsd_state_version: '1.0'
status: planning
progress:
total_phases: 8
completed_phases: 0
total_plans: 0
completed_plans: 0
percent: 0
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-07-29)
**Core value:** A third-party developer can publish an app via the signed/decentralized registry and a user can install it on their node — manifest-driven, rootless, secure, robust.
**Current focus:** Phase 1 — Federation & Mesh Hardening
## Current Position
Phase: 1 of 8 (Federation & Mesh Hardening)
Plan: 0 of TBD in current phase
Status: Ready to plan
Last activity: 2026-07-29 — Inserted Phase 1 (Federation & Mesh Hardening) and Phase 2 (UI Performance) per user priority; prior phases renumbered 38
Progress: [░░░░░░░░░░] 0%
## Performance Metrics
**Velocity:**
- Total plans completed: 0
- Average duration: —
- Total execution time: —
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| - | - | - | - |
## Accumulated Context
### Roadmap Evolution
- Phase 1 added (2026-07-29): Federation & Mesh Hardening — user-directed top priority (node removal/sync issues, mesh attachment parity incl. demo); prior phases shifted down
- Phase 2 added (2026-07-29): UI Performance — slow tab switches and secondary screens; prior phases shifted down
- FED-05 added to Phase 1 (2026-07-29): inter-node Lightning channel-opening UX (share node URI, pick trusted/federated nodes by hostname, request channels with public nodes); UI tested on :8100 dev preview against archi-dev before deploy
- FED-06 added to Phase 1 (2026-07-29): on-brand paid-tick animation — screensaver ring + EQ segments (reuse ScreensaverRing.vue compact) replacing the success burst in SendBitcoinModal.vue
### Decisions
Decisions are logged in PROJECT.md (10 locked ADRs in the `<decisions>` block + milestone decisions table). Recent decisions affecting current work:
- Milestone version = 1.8.0-alpha (decided 2026-07-08)
- Phase-3 Quadlet default-flip is gated on the second-node gate reporting clean (do fresh, never stage uncommitted)
- Workstream D (DHT distribution) deferred to v2 — design-only backlog
- Canonical manifest schema = `core/container/src/manifest.rs` (code wins over spec doc)
### Pending Todos
None yet.
### Blockers/Concerns
- [Phase 1] Federation tombstone fix touches trust code — fix carefully, re-verify with `tests/multinode/smoke.sh`, don't patch blind
- [Phase 3] Multinode gate on archy-x250-beta was launched 2026-07-01 (log on-node); verify outcome before re-running
- [Phase 5] Fleet registry flip awaits explicit user authorization + timing call
- [Phase 6] Strengthened ADR-009 validation may reject existing catalog apps — audit manifests before enforcement lands
- [Global] Live OTA fleet: deploy to the dev pair before any OTA; gate re-runs required after orchestrator changes; some verification is user/hardware-gated (radios, on-device tests)
## Deferred Items
| Category | Item | Status | Deferred At |
|----------|------|--------|-------------|
| Distribution | DIST-01 DHT/iroh backbone (workstream D) | v2 | 2026-07-29 |
| Fleet | FLEET-01 Bitcoin multi-version fleet OTA (user-gated) | v2 | 2026-07-29 |
| Fleet | FLEET-02 per-app deep health assertions (~34 apps) | v2 | 2026-07-29 |
| Fleet | FLEET-03 LUKS2 data-partition encryption | v2 | 2026-07-29 |
## Session Continuity
Last session: 2026-07-29
Stopped at: Roadmap + state initialized from ingest; next step is `/gsd-plan-phase 1`